Renovation process
- 2017/08:Planning for NICU Emergency Surgical Area
- 2017/12:Propose the "Comprehensive Renovation Plan for Section 83"
- 2018/01:Start visiting and collecting relevant information
- 2018/08:Complete the preliminary concept and report
- 2018/09:Formally propose the budget plan for house renovation
- 2019/03:Approve the budget for house renovation
- 2019/05:Complete the ward relocation plan during the renovation period
- 2019/07 ~ 2019/08: Participate in the Yonglin Healthcare Design Workshop and establish the initial design
- 2019/12:Complete the bidding for supervision and design
- 2020/03:Complete detailed design and adjustment of the relocation plan
- 2020/07:Complete the bidding for various projects and the relocation of the wards
- 2020/09/01:Start construction
- 2021/02/28:Completion and gradual acceptance
- 2021/03/31:Obtain the interior decoration certificate and complete the acceptance
- 2021/04/20:Complete the ward inspection by the Health Bureau
- 2021/04/23: Start trial operation
- 2021/05/04:Grand opening